Transportation Investment Act Your Penny, Your Progress
Details
Project
TiaNumber
2
County
Candler
Band
2:2027 to 2029
BandCode
02
Project Type
Grade Drain Base and Pave
ProjectTypeCode
Grade Drain Base and Pave
Project Status
Inactive
Project Name
Candler-Piney Grove Rd
Project Website
Project PDF
PI No.
PI-0018462
Regional Comission
Heart of Georgia Altamaha
Original Budget
372113
Original Budget
372113
Invoiced to Date
$0.00
Invoiced to Date
0
Regional Project ID
HG-Candle-002
Photos
Congressional District
12
Description
Piney Grove RD (CR #177) Paving begins at GA HWY 57 and Extends for 0.24 mi to Piney Grove Missionary Baptist Church and Cemetery. The road is currently a County maintained dirt road however some realignment will be required to move the back slope away from existing gravestones. Paving will stop 20’ beyond the existing church parking lot.